QW 203

Status
Not open for further replies.

JATE

Mechanical
Jan 10, 2014
57
Can you help me:

If ASME IX said:

QW-203 LIMITS OF QUALIFIED POSITIONS FOR PROCEDURES Unless specifically required otherwise by the welding variables (QW-250), a qualification in any position qualifies the procedure for all positions

Then Why piping are tested to qualify wps position 6g , if a 1G position is enough


Thanks

JATE





 
Replies continue below

Recommended for you

It is a supplementary essential variable when impact testing is required. Qualification in vertical up position qualifies all positions when impact testing is required.
 