Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

R Stamp (ASME Code)

Status
Not open for further replies.

Bahruni

Industrial
May 24, 2014
4
Dear Sirs,

I have problem which some part miss installed on the inside pressure vessel during fabrication.
please inform whether R stamp is required or not after missing part installed?

Best Regard
Bahruni

 
Replies continue below

Recommended for you

If welding to be done, yes but if mecanical attachment then you may not need
 
First, what does the local Jurisdiction require for pressure vessel weld repairs? Some Jurisdictions do not regulate pressure vessels so you can use either the NBIC or API 510.
 
Similar to a post last week. It depends on where the vessel is and whether or not it has been put into service. If the vessel is still at the shop, it is not a repair. If the vessel is delivered to site but has not been put into service, it is not a repair (as is the case in my jurisdiciton). You may be able to do the work under original code of construction (Section VIII?) without additional stamps or nameplate modifications. Consult your local AI for final answer.
 
Code construction is considered as complete when the data report is signed and vessel stamped.
It has nothing to do with "whether put in service" or "still in shop not delivered".

For R stamp on missing part, it depends on various factors: Whether the vessel was PWHT, whether impact tests are required, Mr Bahruni should talk to his AI
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor