campbelltc
Structural
- Sep 21, 2011
- 27
We're designing a floor slab for an airport hanger where the concrete slab on grade has radiant floor heat in the slab. The pipes for the heat are supposed to be in the top 5" of the slab. The design software for concrete pavement tells us that it needs to be 8.5" thick, so we went with a 10" slab with #4 @ 12 ew top and bot (before knowing the pipes need to be high, as we usually use radiant heat in thinner slabs and just pour over the pipes). A radiant heat specialist said they cannot hang the pipes from the top steel (my preference). They asked if the slab can be poured in two 5" thick sections, laying the mat on the lower section before placing the upper section. Obviously that creates a plane of weakness, but if up to you, how would you detail that slab? Pour the lower portion with a heavy broom finish? Bonding agent on the first pour? Is there another way to finish to get a better bond? Dowels between the two layers?
I was putting CJ's in the slab at 25' on center. Go to 15' max?
Thanks.
I was putting CJ's in the slab at 25' on center. Go to 15' max?
Thanks.