My question is should code required RT be conducted before or after PWHT. My opinion is after as the weld is not complete until all of the essential variables of the WPS has been met which includes PWHT.
Follow along with the video below to see how to install our site as a web app on your home screen.
Note: This feature may not be available in some browsers.
kingnero said:I'm no expert in RT, but is it sensitive enough to detect reheat cracking (or other microcracking) ?