chicopee
Mechanical
- Feb 15, 2003
- 6,199
Referenced structure is over 100 years old and is to be raised 2' above its foundation. Foundation wall is of field stone for the first five feet and of motared brick for about another foot.
The plan is to raise the house with wide flange beams supported by screw jacks to be placed throughout the cellar as closely as possible to the footing. Since it will be impossible to actually place these screw jacks directly under the exterior walls, holes will be made along the length of the foundation to place additional jacks(hydraulic) directly under the sill plates. As the screw jacks are turned a few threads each, the hydraulic jacks will then be raised to offer additional supports to the exterior walls, in turn theses walls will be shimmed to offer continuous support as the existing foundation would offer. The process will be repeated numerous times to achieve a 2' raise.
The house plan is somewhat rectangular. The center one third of the plan area is wider by 4' on one side and 2' on the opposite side than then the end areas. There are two beams at the floor plan discontinuties for the support of the floor joists.
IS THIS PLAN REALISTIC OR TOO MUCH WORK IS BEING CREATED WITH THE INTRODUCTION OF THE HYDRAULIC JACKS? HAS ANYONE EXPERIENCED SIMILAR SITUATIONS AND SUCCESSFULLY RAISED SUCH HOUSE? INPUT IS GREATLY APPRECIATED.
The plan is to raise the house with wide flange beams supported by screw jacks to be placed throughout the cellar as closely as possible to the footing. Since it will be impossible to actually place these screw jacks directly under the exterior walls, holes will be made along the length of the foundation to place additional jacks(hydraulic) directly under the sill plates. As the screw jacks are turned a few threads each, the hydraulic jacks will then be raised to offer additional supports to the exterior walls, in turn theses walls will be shimmed to offer continuous support as the existing foundation would offer. The process will be repeated numerous times to achieve a 2' raise.
The house plan is somewhat rectangular. The center one third of the plan area is wider by 4' on one side and 2' on the opposite side than then the end areas. There are two beams at the floor plan discontinuties for the support of the floor joists.
IS THIS PLAN REALISTIC OR TOO MUCH WORK IS BEING CREATED WITH THE INTRODUCTION OF THE HYDRAULIC JACKS? HAS ANYONE EXPERIENCED SIMILAR SITUATIONS AND SUCCESSFULLY RAISED SUCH HOUSE? INPUT IS GREATLY APPRECIATED.