kmead
Structural
- Jan 25, 2006
- 56
Hi,
I have a client who wants to add a second floor to an existing metal building. However, the existing metal frames need to be raised about 5 feet in order to allow for adequate headroom. The frames consist of wide flange constant width columns, and tapered beams that frame over the columns, the beams are spliced in the middle. The building is about 40 feet wide, and the frames are spaced about 24 feet o.c.
My solution is to raise the frames onto new 5 foot high concrete piers that would be adequately anchored to the existing piers to resist any lateral loads. The base plate connection will be designed for the appropriate loads and moments.
The new floor load will be completely independent of the existing framing since I am planning on adding new beams and columns inside of the existing frames.
I will also have to check the seismic adequacy of the building since I'm adding a considerable dead load.
I just wanted to see if anyone thinks that there's something else I should be worrying about besides the issues I mentioned above. I've never done this kind of project before and I wanna make sure I'm not overseeing something obvious. Thanks.
I have a client who wants to add a second floor to an existing metal building. However, the existing metal frames need to be raised about 5 feet in order to allow for adequate headroom. The frames consist of wide flange constant width columns, and tapered beams that frame over the columns, the beams are spliced in the middle. The building is about 40 feet wide, and the frames are spaced about 24 feet o.c.
My solution is to raise the frames onto new 5 foot high concrete piers that would be adequately anchored to the existing piers to resist any lateral loads. The base plate connection will be designed for the appropriate loads and moments.
The new floor load will be completely independent of the existing framing since I am planning on adding new beams and columns inside of the existing frames.
I will also have to check the seismic adequacy of the building since I'm adding a considerable dead load.
I just wanted to see if anyone thinks that there's something else I should be worrying about besides the issues I mentioned above. I've never done this kind of project before and I wanna make sure I'm not overseeing something obvious. Thanks.