ramconcept-rapt
Structural
- Jan 6, 2018
- 5
Ram concept - AS 3600.2009
Hi everyone, When I first looked into load combination of AS.3600-2009 for prestressed concrete, the initial service load combo in Standard is 0.9SW + 1.15P, which is different from 0.8SW + 1.15P in Ramconcept manual. Can anyone explained me why?
Hi everyone, When I first looked into load combination of AS.3600-2009 for prestressed concrete, the initial service load combo in Standard is 0.9SW + 1.15P, which is different from 0.8SW + 1.15P in Ramconcept manual. Can anyone explained me why?