PUEngineer
Structural
- Oct 31, 2008
- 98
We did the structural design of a building where rammed aggregate piers were used to provide a better soil bearing pressure. In addition, at the lateral bracing locations, they were required to provide some uplift resistance.
The rammed aggregate pier submittal came through with notes about the EOR verifying the embedded length of the uplift anchor into the column foundation. This seems like it should fall into the rammed aggregate pier supplier's scope. They set the force in the anchor based on the number of uplift piers used to resist the total force. They set the size of the embed plate in the concrete foundation based on bearing. They set the locations of the uplift piers.
The one calculation they balk at providing is a complete calculation showing the anchor won't pullout of the foundation. Has anyone else experienced this?
The rammed aggregate pier submittal came through with notes about the EOR verifying the embedded length of the uplift anchor into the column foundation. This seems like it should fall into the rammed aggregate pier supplier's scope. They set the force in the anchor based on the number of uplift piers used to resist the total force. They set the size of the embed plate in the concrete foundation based on bearing. They set the locations of the uplift piers.
The one calculation they balk at providing is a complete calculation showing the anchor won't pullout of the foundation. Has anyone else experienced this?