krisys
Electrical
- May 12, 2007
- 458
We have five (5) nos. of 11 kV Ring Main Unit (RMU) Loops supplied from a 11 kV container substation. Each loop (distribution Ring) has two feeders from the same substation. Even if one feeder or one RMU is one outage, the other RMU loads can be supplied. Needless to say without a redundancy of source!
The RMU is feeds one transformer rated 11kV/433V, 150 kVA. The downstream has one main Distribution Board. The main Distribution Board feeds the loads such as UPS, 5.5kW motor driven pumps, Motor operated valves etc.
We have situations where we may sometimes need to keep the RMU and the Loads connected to the RMU off for a prolonged period of time, say one (1) to eight (8) months. In this case, while resuming the power supply to the RMU, do we need to re-commission the system or we can just energize the system and take it into service?
Is there any regulatory requirements or industry practice governing this aspect.
In my opinion, it makes sense to perform some basic tests/inspection before energizing the system after a prolonged duration n outage. But up to what level is what is intriguing me.
The RMU is feeds one transformer rated 11kV/433V, 150 kVA. The downstream has one main Distribution Board. The main Distribution Board feeds the loads such as UPS, 5.5kW motor driven pumps, Motor operated valves etc.
We have situations where we may sometimes need to keep the RMU and the Loads connected to the RMU off for a prolonged period of time, say one (1) to eight (8) months. In this case, while resuming the power supply to the RMU, do we need to re-commission the system or we can just energize the system and take it into service?
Is there any regulatory requirements or industry practice governing this aspect.
In my opinion, it makes sense to perform some basic tests/inspection before energizing the system after a prolonged duration n outage. But up to what level is what is intriguing me.