i am working on a geotechnical project. Part of the project consists of running 108 (single samples) consolidated undrained triaxial tests. I need to finish it in 90 calendar days. I am trying to come up with a plan of action.I am wondering how long will it take to run each test (saturation, consolidation and shear). I really appreciate if some one could provide me time frame for each stage.
Thanks
i am working on a geotechnical project. Part of the project consists of running 108 (single samples) consolidated undrained triaxial tests. I need to finish it in 90 calendar days. I am trying to come up with a plan of action.I am wondering how long will it take to run each test (saturation, consolidation and shear). I really appreciate if some one could provide me time frame for each stage.