QCJT
Industrial
- Feb 16, 2011
- 52
Hello All,
My Client wants to replace some of the old equipment in the plant and the question is weather to replace or not the piping which is connected to this equipment, which is also of the same age (20 years). At this moment I dont have any maintenance inpsection reports and do not have any idea about remaining wall thickness of the piping or their condition but I want to hear from you the general approach to these kind of issues. There are pros and cons in both scenarios:
Replacing pros: 1) We will cut the pipes out in any case for enabling the removal and replacement of equipment. The removed piping maybe discarded and replaced with new ones, without loosing much time as most can be prefabricated
2) With new piping we can have sufficient overlength to avoid shortages
Replacing cons: 1) We are not replacing all of the piping in the plant, the cut out sections that are to be replaced aren't necessarily the worst (most corroded) part of the pipingı 2) introducing new, thicker wall pipes may cause some issues during fit up.
Reusing pros: 1) much less work and costs (even insulation could be reused on certain parts); 2) same wall thickness as the remaining pipe
Reusing cons: 1) unknown condition of the steel (grain size due to pwht, corrosion and etc); 2) potential shortages of material due to cutting, grinding etc.
Note: if reusing, we plan to make cuts on the center of the weld, prepeare the bevel and lpt for cracks and only then weld. If we need to remove by grinding more steel than the weld metal, we will compensate by buttering in addition an extra length of new pipe will be available just in case we need to replace a section.
Piping is mostly carbon steel (among them also P22), some 15NiCuMoNb5 steel and some A182, 304H.
What would be your primary concerns in case of reusing and which option would you be inclined for? Looking forward to all critical and informative comments.
My Client wants to replace some of the old equipment in the plant and the question is weather to replace or not the piping which is connected to this equipment, which is also of the same age (20 years). At this moment I dont have any maintenance inpsection reports and do not have any idea about remaining wall thickness of the piping or their condition but I want to hear from you the general approach to these kind of issues. There are pros and cons in both scenarios:
Replacing pros: 1) We will cut the pipes out in any case for enabling the removal and replacement of equipment. The removed piping maybe discarded and replaced with new ones, without loosing much time as most can be prefabricated
2) With new piping we can have sufficient overlength to avoid shortages
Replacing cons: 1) We are not replacing all of the piping in the plant, the cut out sections that are to be replaced aren't necessarily the worst (most corroded) part of the pipingı 2) introducing new, thicker wall pipes may cause some issues during fit up.
Reusing pros: 1) much less work and costs (even insulation could be reused on certain parts); 2) same wall thickness as the remaining pipe
Reusing cons: 1) unknown condition of the steel (grain size due to pwht, corrosion and etc); 2) potential shortages of material due to cutting, grinding etc.
Note: if reusing, we plan to make cuts on the center of the weld, prepeare the bevel and lpt for cracks and only then weld. If we need to remove by grinding more steel than the weld metal, we will compensate by buttering in addition an extra length of new pipe will be available just in case we need to replace a section.
Piping is mostly carbon steel (among them also P22), some 15NiCuMoNb5 steel and some A182, 304H.
What would be your primary concerns in case of reusing and which option would you be inclined for? Looking forward to all critical and informative comments.