sshep
Chemical
- Feb 3, 2003
- 761
Friends,
What is the formula for calculating the reactive force from a liquid discharge? I am expecting a function of density, flow, velocity squared, etc and am asking for some quick help.
This is the story: I come back from holiday to find a piping wreck at one of our cooling towers. The story I get is that a pump was started using a "minimum flow line" back to the tower. This is a 12" line without any restriction running from a pump discharge (rated at 3050 cubic meters/minute) and about 4 or 5 meters up the side of the tower. It has two horizontal bends at the top that seem to match a reactive twisting action of the piping wreckage. The story that I got from the RCA team was that some sort of a hammer occured, but I think the answer is much simpler. The team did not consider a reactive force acting on a long moment arm. I made an inquiry to the manager as to whether the piping anchor at the top of the line might have failed, and was surprised to be told that the piping was not anchored. There was supposed to be a U-bolt anchor, but apparently it was never installed. This makes me even more suspicious of a reactive force causing the piping wreck. Anyway, this is the story, so any help with a formula or comment is appreciated. If I calculate the force, I can get a mechanical engineer to comment on whether my theory is plausible.
best wishes always,
sshep
What is the formula for calculating the reactive force from a liquid discharge? I am expecting a function of density, flow, velocity squared, etc and am asking for some quick help.
This is the story: I come back from holiday to find a piping wreck at one of our cooling towers. The story I get is that a pump was started using a "minimum flow line" back to the tower. This is a 12" line without any restriction running from a pump discharge (rated at 3050 cubic meters/minute) and about 4 or 5 meters up the side of the tower. It has two horizontal bends at the top that seem to match a reactive twisting action of the piping wreckage. The story that I got from the RCA team was that some sort of a hammer occured, but I think the answer is much simpler. The team did not consider a reactive force acting on a long moment arm. I made an inquiry to the manager as to whether the piping anchor at the top of the line might have failed, and was surprised to be told that the piping was not anchored. There was supposed to be a U-bolt anchor, but apparently it was never installed. This makes me even more suspicious of a reactive force causing the piping wreck. Anyway, this is the story, so any help with a formula or comment is appreciated. If I calculate the force, I can get a mechanical engineer to comment on whether my theory is plausible.
best wishes always,
sshep