Christine74
Mechanical
- Oct 8, 2002
- 556
I've noticed that pressure vessels built in the 1940s and 1950s were often shop-hydrotested at pressures much higher than 1.5X (now 1.3X) required by the Code and was curious to understand why. Some vessels that were carbon steel construction with design temperatures below 650 F (temperature correction factor = 1.0) were hydrotested at more than 2X the listed MAWP. This applies to ASME Section VIII (there were no Divisions I/II/III yet) as well as API-ASME pressure vessels.
Were the higher hydrotest pressures due to special Code requirements in place at the time or was it just a common industry practice during that period?
Thanks.
-Christine
Were the higher hydrotest pressures due to special Code requirements in place at the time or was it just a common industry practice during that period?
Thanks.
-Christine