Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations IDS on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

rebar development/lap length

Status
Not open for further replies.

KZF1

Structural
Jul 20, 2009
5
I have a 5' high, 8" thick, cast-in-place cantilever retaining wall. The contractor installed the footing dowels with the vertical leg of the bar 3" too short to have a proper "Class B" tension lap with the vertical bars of the wall.

Is there a procedure to calculate a reduced capacity of the wall based on this improper lap length?
 
Replies continue below

Recommended for you

I'd reduce your available steel tension capacity by the same percentage that the lap length has been reduced. Here, that will result in a reduction of moment capacity by the same percentage +/-.

I like to debate structural engineering theory -- a lot. If I challenge you on something, know that I'm doing so because I respect your opinion enough to either change it or adopt it.
 
I generally echo KootK's approach. For me though, if the actual bars were #6 (.44 in^2) and As,pro/As,req landed me at .38 in^2, I would round down to .31 in^2 (#5).

"It is imperative Cunth doesn't get his hands on those codes."
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor