windrunner888
Civil/Environmental
- May 8, 2006
- 4
I encounter an approach that I am not quite familiar with. I use arbitrary number in the description below:
A 15’ long concrete drilled pier was reinforced using 10’ long post-installed rebars. The additional rebars have 4’ development length.
Resistance A: original rebar + post-installed rebar
Resistance B: original rebar
From top to bottom, the engineer used:
0-6’: Resistance A
6’-10’: Resistance A at 6’, linearly reduced to resistance B at 10’
10’-15’: Resistance B
I am wondering if using partial resistance of rebar (6’-10’) is justified? I usually don’t consider contribution of rebar within its own development length (hard cut-off, I would use resistance B from 6’ to bottom). Any codes that allowing (or disallowing) it?
Thank you!
A 15’ long concrete drilled pier was reinforced using 10’ long post-installed rebars. The additional rebars have 4’ development length.
Resistance A: original rebar + post-installed rebar
Resistance B: original rebar
From top to bottom, the engineer used:
0-6’: Resistance A
6’-10’: Resistance A at 6’, linearly reduced to resistance B at 10’
10’-15’: Resistance B
I am wondering if using partial resistance of rebar (6’-10’) is justified? I usually don’t consider contribution of rebar within its own development length (hard cut-off, I would use resistance B from 6’ to bottom). Any codes that allowing (or disallowing) it?
Thank you!