ChemStel
Chemical
- Jan 23, 2008
- 8
I have read the other threads regarding drainage on eng-tips but couldn't seem to find the answers I need.
I have a vertical, cylindrical, dished end vessel filled with water. Inside diameter is 394mm. Working height is 1313mm. Working volume is 160 litres. Inside diameter of outlet nozzle, located on bottom of vessel is 27mm. Drain line inside diameter is 18.4mm and is roughly 50mm below nozzle. Drain line is about 7m long. Drain line is a straight run on the floor.
The drainage time has been measured on site to be about 16 mins, which is causing a bottle-neck in the process. Are there any ways in which I can reduce the drainage time?
Will increasing the drain line diameter help even though the nozzle diameter is fixed? Does height have any impact on drainage time?
I have tried calculating drainage time using this formula (From Crowe, Elger & Roberson - Engineering Fluid Mechanics) : t = 2AT/(SQRT(2/g).A1).(h0^1/2 – h^1/2) and the answer I get is 2 mins, so I have come to the conclusion that above formula is only valid for direct discharge to atmosphere and does not take discharge pipework into account.
I then tried calculating discharge using the Crane manual (E.g 4-19), which is for discharge flow from a reservoir with constant head through a piping system (Q = 0.2087 x d^2 x SQRT(hl / K). My real-life application, however doesn't have a constant head, so I assumed the head to be half of the starting height. This gave me an answer very close to the actual measured value. Does this sound like the correct way of calculating this, or is there a way I can account for the changing level, or will the change in answer just be negligible. This example takes into account the head. Will raising my vessel higher reduce the drainage time, I can't see how?
I have a vertical, cylindrical, dished end vessel filled with water. Inside diameter is 394mm. Working height is 1313mm. Working volume is 160 litres. Inside diameter of outlet nozzle, located on bottom of vessel is 27mm. Drain line inside diameter is 18.4mm and is roughly 50mm below nozzle. Drain line is about 7m long. Drain line is a straight run on the floor.
The drainage time has been measured on site to be about 16 mins, which is causing a bottle-neck in the process. Are there any ways in which I can reduce the drainage time?
Will increasing the drain line diameter help even though the nozzle diameter is fixed? Does height have any impact on drainage time?
I have tried calculating drainage time using this formula (From Crowe, Elger & Roberson - Engineering Fluid Mechanics) : t = 2AT/(SQRT(2/g).A1).(h0^1/2 – h^1/2) and the answer I get is 2 mins, so I have come to the conclusion that above formula is only valid for direct discharge to atmosphere and does not take discharge pipework into account.
I then tried calculating discharge using the Crane manual (E.g 4-19), which is for discharge flow from a reservoir with constant head through a piping system (Q = 0.2087 x d^2 x SQRT(hl / K). My real-life application, however doesn't have a constant head, so I assumed the head to be half of the starting height. This gave me an answer very close to the actual measured value. Does this sound like the correct way of calculating this, or is there a way I can account for the changing level, or will the change in answer just be negligible. This example takes into account the head. Will raising my vessel higher reduce the drainage time, I can't see how?