purode333
Mechanical
- Sep 16, 2016
- 58
Dear sir/all,
We have 2.5 KM of C.S. pipe line, and we have start the hydro test at 5pm with 18kg/cm2 and as per holding time of two hours , it is completed at 7pm , without any leakage or seepage.
But after completion of 2 hrs., pressure decrease by 1hrs. and it found 17kg/cm2.
We stated that due to decrease in temperatures, pressure also decrease. but client not ready to accept.
Pls help.
Design pressure is 12kg/cm2 and hydro test pressure is 18 kg/cm2.
Regards
Prasad
We have 2.5 KM of C.S. pipe line, and we have start the hydro test at 5pm with 18kg/cm2 and as per holding time of two hours , it is completed at 7pm , without any leakage or seepage.
But after completion of 2 hrs., pressure decrease by 1hrs. and it found 17kg/cm2.
We stated that due to decrease in temperatures, pressure also decrease. but client not ready to accept.
Pls help.
Design pressure is 12kg/cm2 and hydro test pressure is 18 kg/cm2.
Regards
Prasad