Was wondering where I could find or what are the requirements for installing repads at nozzel stub-in locations on a system header if any. Presently I am looking at a project that has a 20" header with 16" stub-ins both standard wall thickness. I am thinking that it would be in Section VIII Div 2 but not 100% sure.
Any info will be greatly appreciated.
Thanks,
TD