rmillercwi
Materials
- Jul 19, 2006
- 76
A severed tube was found in a j-groove tube panel after several years in service. The severed tube was given to us for analyisis. After measuring the failed weld surface area, it was determined that improper weld technique/insuficient joint opening was employed. The suggested repair method is to increase the fillet weld size significantly. Naturaly the customer would like to avoid PWHT if possible. 2" od tube, 150mw, slip joint design, p5a to p5a. Suggested weld process GTAW. No impact requirements.
Asuming the repair process to fall under NBIC requirements,
I have read the repair section PART RD welding method 4 in the NBIC code. I understand the pre-requisite to actual work is a working WPS without PWHT created to the rules of the original code of construction. The process of repair is straightfoward with exception of the post heating. The postheating is used to remove any remaining Hydrogen. Why would there be any hydrogen if the welding process was performed with GTAW?
Does it make sense to even consider adding weld to each and every tube to header weld in a P5A configuration without PWHT?
Please advise
Asuming the repair process to fall under NBIC requirements,
I have read the repair section PART RD welding method 4 in the NBIC code. I understand the pre-requisite to actual work is a working WPS without PWHT created to the rules of the original code of construction. The process of repair is straightfoward with exception of the post heating. The postheating is used to remove any remaining Hydrogen. Why would there be any hydrogen if the welding process was performed with GTAW?
Does it make sense to even consider adding weld to each and every tube to header weld in a P5A configuration without PWHT?
Please advise