canman
Civil/Environmental
- Feb 28, 2003
- 34
Hello all,
I'm a civil engineer in the Southern California region that needs an answer to what most will probably regard as an easy question. I design a lot of fire protection systems from the point of connection at existing watermains in public streets up to private on-site hydrants and the base of fire risers at new buildings. I do not design the building sprinkler systems themselves, only outside the buildings. What does N.F.P.A. 13 or 24 say about how much flow needs to be calculated for when designing the required flow for both a private hydrant and fire riser at a building? For instance, let's say I was assigned a task to design a new fire system for a private hydrant that requires 1500 gpm, at a minimum residual pressure of 20 psi, in addition to the 500 gpm required at the base of a riser to feed a 4,500 s.f. light hazard occupancy type building. Do my overall calculations need to combine the 1500 gpm for the hydrant and the 500 gpm for the building? Obviously designing for the 2000 gpm would make a difference in the price of the pipe, valves, backflow equipment, etc. I deal with lots of different City & County fire authorities and some require the calcs to account for both while others only require calcs for the larger number of 1500 gpm, thus the confusion on my end. Thanks for your input in advance.
Regards,
Canman
I'm a civil engineer in the Southern California region that needs an answer to what most will probably regard as an easy question. I design a lot of fire protection systems from the point of connection at existing watermains in public streets up to private on-site hydrants and the base of fire risers at new buildings. I do not design the building sprinkler systems themselves, only outside the buildings. What does N.F.P.A. 13 or 24 say about how much flow needs to be calculated for when designing the required flow for both a private hydrant and fire riser at a building? For instance, let's say I was assigned a task to design a new fire system for a private hydrant that requires 1500 gpm, at a minimum residual pressure of 20 psi, in addition to the 500 gpm required at the base of a riser to feed a 4,500 s.f. light hazard occupancy type building. Do my overall calculations need to combine the 1500 gpm for the hydrant and the 500 gpm for the building? Obviously designing for the 2000 gpm would make a difference in the price of the pipe, valves, backflow equipment, etc. I deal with lots of different City & County fire authorities and some require the calcs to account for both while others only require calcs for the larger number of 1500 gpm, thus the confusion on my end. Thanks for your input in advance.
Regards,
Canman