senthil83
Mechanical
- Jun 26, 2012
- 66
Dear All,
Please clarify me whether the PWHT(Post Weld Heat treatment) is required to be done for welding a 25mm thick plate to a hanger rod of dia 80mm which is at the temperature of around 400 deg. carrying a load of 10 tons.
Also please let me know in which code these requirements are mentioned.
thanks
Please clarify me whether the PWHT(Post Weld Heat treatment) is required to be done for welding a 25mm thick plate to a hanger rod of dia 80mm which is at the temperature of around 400 deg. carrying a load of 10 tons.
Also please let me know in which code these requirements are mentioned.
thanks