Does anyone know how I would go about filtering the Resource Usage report to only display tasks which have hours displayed during the specified period.

My report is displaying all tasks for each resource even if I am specifying, for example, only a four week period.

Thanks!

sobuck
s_obuck@msn.com
 
Replies continue below

Recommended for you

What do you mean by "specify a four week period"?

If you filter for finish> start of period AND start <end of period, it should display ony those tasks that have hours with the period, but it will still display hours that fall outside of the period for those tasks that have hours within the period.

You can simply copy the entire table into Excel and muck with it there if you choose.