betonboer
Civil/Environmental
- Jul 26, 2010
- 3
I want to schedule a task of 3 x 1/2 day/week for 20 weeks.
These 1/2 days are always on tuesday, thursday and friday.
When I use a recurring task, everything goes well untill I look at the resource graph. There it says 8 hours/day instead of the expected 4 hours/day.
I think (hope) it's set to "days" instead of "hours" somewhere.
But where do I set the resourcegraph to display (and calculate) with the real hours when using a recurring task?