EireChch
Geotechnical
- Jul 25, 2012
- 1,309
Hi all,
I am using Wallap to design a 3.5m high basement wall. The soil is made ground sand/silt layer to 1.5m over clay to 20m plus (shear strength of 50-125kPa). There was some discussion on what type of retaining wall to use but we have arrived at a secant piled wall. For a worst case ULS event (i.e. factored soil parameters, groundwater at 1m below surface and 10kPa surcharge), to achieve a FoS of 1.2 i need roughly 12m of embedment. (Seems excessive to me,but thats what WALLAP is telling me, i suppose there is a lot of load with reduced soil parameters. I am newish to Wallap so my design will be check by another engineer and also by my line manager.
The top of the wall will eventually be restrained with a concrete slab so i would like to consider that as a prop/strut force.
When modelling props/struts in WALLAP gives the options of youngs modulus or Pre stress or both. What would be the most appropriate way to model this as to simulate the restraint provided by the slab. Not specifically i WALLAP but i general good practice.
I am using Wallap to design a 3.5m high basement wall. The soil is made ground sand/silt layer to 1.5m over clay to 20m plus (shear strength of 50-125kPa). There was some discussion on what type of retaining wall to use but we have arrived at a secant piled wall. For a worst case ULS event (i.e. factored soil parameters, groundwater at 1m below surface and 10kPa surcharge), to achieve a FoS of 1.2 i need roughly 12m of embedment. (Seems excessive to me,but thats what WALLAP is telling me, i suppose there is a lot of load with reduced soil parameters. I am newish to Wallap so my design will be check by another engineer and also by my line manager.
The top of the wall will eventually be restrained with a concrete slab so i would like to consider that as a prop/strut force.
When modelling props/struts in WALLAP gives the options of youngs modulus or Pre stress or both. What would be the most appropriate way to model this as to simulate the restraint provided by the slab. Not specifically i WALLAP but i general good practice.