Ride-on laser screeds moving placed rebar during slab-on-grade pours?

Status
Not open for further replies.

engphila

Structural
Jul 10, 2005
21
0
0
US
Does anyone have any experience with ride-on laser screeds moving placed rebar during slab-on-grade pours? I am familiar with the cantilever reach version of these laser screed machines but I am very concerned that the ATV-wheeled versions that operate over placed rebars are being displaced and pushed down during their operations on a double reinforced mat.

The online world appears to be mute on this topic...unless I'm just not looking in the correct areas.

Cheers,
FpM

engphila


engphila
 
Replies continue below

Recommended for you

I would not see the need to use a laser screed on a placement with a double mat of rebar.

Laser screeds are effective for unreinforced or lightly reinforced slabs on grade where finish tolerances are tight.
 