burntcoil
Electrical
- Sep 28, 2011
- 75
Hi everyone,
We have multiple Ring Main Units connected together forming a loop as shown in the attachment. Its a 13.8kV Network. The Ring Loops are fed from a 13.8kV Switchgear, Bus-A is feeding one side of the loop while Bus-B is feeding the other side of the loop. Under normal condition, one of the breaker in the middle of the loop will be open (N.O) thus each breaker in the 13.8kV Switch-gear will feed half of each loop.
How Over-current coordination can be carried out for this loop to work both ways i.e. Breaker on Bus-A shall feed the whole loop, Breaker on Bus-B shall feed the whole loop. What are the practices when doing over-current coordination for such networks.
Thanks
We have multiple Ring Main Units connected together forming a loop as shown in the attachment. Its a 13.8kV Network. The Ring Loops are fed from a 13.8kV Switchgear, Bus-A is feeding one side of the loop while Bus-B is feeding the other side of the loop. Under normal condition, one of the breaker in the middle of the loop will be open (N.O) thus each breaker in the 13.8kV Switch-gear will feed half of each loop.
How Over-current coordination can be carried out for this loop to work both ways i.e. Breaker on Bus-A shall feed the whole loop, Breaker on Bus-B shall feed the whole loop. What are the practices when doing over-current coordination for such networks.
Thanks