Guest
Hi all,
Has anyone had the experience about the design road for the container 40ft. truck across the 2 underground water pipelines which spacing between pipeline is 2.20 m. The pipeline is a steel pipe dia. 1.35m and fy = 36 ksi and buried under ground level 1.50 and 3.00 m repectively? The soil in this area is sandy clay. In my opinion I want to use the structure such as U frame or box culvert without bottom slab to carry truck load and transfer the load to footing of the structure at the level 3.00 m below ground but this method will make the contractor to excavate lots of soil and will delay their program. But if I use a normal road (0.3 m of crushed rock with 0.25 m. of concrete slab above )across the pipeline. I' worried the load from truck will make the problem with the pipeline and I'm not sure how to calculate the pressure over the pipline from the truck load and how to check that pipe can resist this load.
Thank you in advance
Cu73
Has anyone had the experience about the design road for the container 40ft. truck across the 2 underground water pipelines which spacing between pipeline is 2.20 m. The pipeline is a steel pipe dia. 1.35m and fy = 36 ksi and buried under ground level 1.50 and 3.00 m repectively? The soil in this area is sandy clay. In my opinion I want to use the structure such as U frame or box culvert without bottom slab to carry truck load and transfer the load to footing of the structure at the level 3.00 m below ground but this method will make the contractor to excavate lots of soil and will delay their program. But if I use a normal road (0.3 m of crushed rock with 0.25 m. of concrete slab above )across the pipeline. I' worried the load from truck will make the problem with the pipeline and I'm not sure how to calculate the pressure over the pipline from the truck load and how to check that pipe can resist this load.
Thank you in advance
Cu73