SteelPE
Structural
- Mar 9, 2006
- 2,747
I have an odd shaped building where I need to figure out the necessary pitch to the internal drainage system.
Normally I will give a top of joist elevation on my drawings and then give deviations from these elevations at the top of the column locations to help the fabricator with the design. However, I rarely work with odd shaped roofing systems. I am wondering how to figure roof pitch for such structures (see attached).
Normally I would figure roof pitch on the orthogonal axis (take the longest distance to the drain and multiply by .25 and then work from there). These are the red numbers shown on the attached drawing. This gives us some large initial pitches at B-2. One solution is to figure the maximum deviation at the drain than then work out the pitch linearly along line 2 (blue numbers). However, this option gives very little pitch from A-B.
On this project the client wants the perimeter steel all at the same elevation. The perimeter of the building is a load bearing wall system (think masonry). Joist run parallel to numbered lines (to allow for an easier bearing condition, girders run parallel to lettered lines.
Other options:
-Deviate the perimeter steel elevations (this would eliminate the issue, but make determining the top of steel elevation a pain). The client does not want to do this
-Eliminate the column at B-2 to "smooth" out the pitch with the roof members. This may cause other issues with members lengths during shipping.
Anyone have any thoughts?
Normally I will give a top of joist elevation on my drawings and then give deviations from these elevations at the top of the column locations to help the fabricator with the design. However, I rarely work with odd shaped roofing systems. I am wondering how to figure roof pitch for such structures (see attached).
Normally I would figure roof pitch on the orthogonal axis (take the longest distance to the drain and multiply by .25 and then work from there). These are the red numbers shown on the attached drawing. This gives us some large initial pitches at B-2. One solution is to figure the maximum deviation at the drain than then work out the pitch linearly along line 2 (blue numbers). However, this option gives very little pitch from A-B.
On this project the client wants the perimeter steel all at the same elevation. The perimeter of the building is a load bearing wall system (think masonry). Joist run parallel to numbered lines (to allow for an easier bearing condition, girders run parallel to lettered lines.
Other options:
-Deviate the perimeter steel elevations (this would eliminate the issue, but make determining the top of steel elevation a pain). The client does not want to do this
-Eliminate the column at B-2 to "smooth" out the pitch with the roof members. This may cause other issues with members lengths during shipping.
Anyone have any thoughts?