slapjack
Structural
- Feb 6, 2007
- 14
When providing structural framing between bar joists for the support of roof top units, how is the metal roof deck cut to provide chase openings... do they cut the metal deck out for the entire perimeter of the RTU curb or do they only cut the deck where the supply and return chases pass through the roof?
Also, anyone have recommendations for RTU tie-down in high wind zones? Our units are typically supported by W6x9 beams which span between joists under the deck. The RTU curb is then installed over the metal deck.
Thanks!