Dinosaur
Structural
- Mar 14, 2002
- 538
I have access to left over 4x8 concrete cylinders. I have a nine foot high berm behind my house that serves as a poor noise barrier between me and the highway. I would like to terace the berm into three three foot high sections. It seems it should be possible to stack 4x8 concrete cylinders to create a rubble retaining wall.
I have started some rudimentary calculations to get a handle on the project. I have checked sliding with a F-of-S of 1.33 and also overturning. I am using Ka to determine the governing soil pressures. What sort of things are done for making retaining walls from rubble?
There is one section where I may want to combine two walls along a 20 foot length so I would need a 6 foot high section there. This will absolutely require some kind of tie back or deadman if I can get it to work at all.
Before anyone says "Why not use those blocks they sell at the home improvement store?" The answer is, the blocks would cost $15,000 and I would still need some gravel for backfill, etc. I can build the three foot high sections of my project by myself, although it may take several years to complete the project as a "weekend warrior". Right now, I am just stockpiling the cylinders for next years part of the project and doing some calcs to make sure it doesn't all collapse.
Any help would be appreciated. Thanks.
I have started some rudimentary calculations to get a handle on the project. I have checked sliding with a F-of-S of 1.33 and also overturning. I am using Ka to determine the governing soil pressures. What sort of things are done for making retaining walls from rubble?
There is one section where I may want to combine two walls along a 20 foot length so I would need a 6 foot high section there. This will absolutely require some kind of tie back or deadman if I can get it to work at all.
Before anyone says "Why not use those blocks they sell at the home improvement store?" The answer is, the blocks would cost $15,000 and I would still need some gravel for backfill, etc. I can build the three foot high sections of my project by myself, although it may take several years to complete the project as a "weekend warrior". Right now, I am just stockpiling the cylinders for next years part of the project and doing some calcs to make sure it doesn't all collapse.
Any help would be appreciated. Thanks.