rubendar
Computer
- Dec 17, 2017
- 2
What value of ruling span to take to spot tower to a new distribution electric line?. it´s necesary to assume one value?.
To validate ruling span chosen may be calculating error between ruling span assumed and real (once tower are spotted). if error is lower for example 5%, then ruling span initially assumed is acceptable, on the contrary start again taking now ruling span calculated, iterate until to get the error acceptable. it´s this procedure correct?. are there another methodology?.
Best regards,
Ruben
To validate ruling span chosen may be calculating error between ruling span assumed and real (once tower are spotted). if error is lower for example 5%, then ruling span initially assumed is acceptable, on the contrary start again taking now ruling span calculated, iterate until to get the error acceptable. it´s this procedure correct?. are there another methodology?.
Best regards,
Ruben