How can I show a column that gives me a running duration of the project. Ex: Task 1 takes 2 days; Task 2 takes 3 days. I'd like a column that shows total duration to date "5 Days".
 
Replies continue below

Recommended for you

If they are linked with the proper predecessor relationship, you can simply make them all subtasks, in which case, the roll-up will have the cumulative duration

TTFN
 
Alternatively you could, using tools/options, check the box against "Show project summary task". This will put in a task with ID "0" and will show you your whole project as a summary bar giving you all the information that all the tasks have, for example duration, work, baseline information etc.