bmoorthy
Mechanical
- May 29, 2003
- 457
In a U stamped Pressure vessel SA 420 WPL6 is to be used.
The vessel is required to be postweld heat treated.
There are no requirements to follow other that ASME (That is client specification says "All presure vessel shall be designd and fabricated to ASME Sec VIII Div 1 as per desin data (Design data given)
Question 1:: Noting that ASME Sec VIII Div 1 UCS does not call for simulation heat treatment for P1 material, yet as per the clause 7.4 of SA 420 WPL 6 (As embedded below)Is it necessary (In order to meet the ASME requirement) for the vessel manufacturer to inform the fitting supplier that the vessel is going to be used in a vessel and that the vessel is going to be post weld heat treated and the fitting need simulation heat treatment?
Clause 7.4 from A 420 WPL6
7.4 When the fittings are to be post-weld heat treated after being welded by the purchaser and when so specified in the order, the test specimens shall be subjected to the same post-weld heat treatment. The purchaser shall use the postweld heat treatment shown in Table 2, unless otherwise
specified in the order.
Question 2) Does the words " When specified so" imply an obligation on the part of vessel manufacturer to inform the manufacturer of the fitting?
Question 3) IF the vessel manufactuer does mention the vessel is being heat treated, is it mandatory for the fitting manufacturer to subject the test specimens to the same post-weld heat treatment prior to testing (Even if the vessel manufacturer does not call for Simulated testing).
The vessel is required to be postweld heat treated.
There are no requirements to follow other that ASME (That is client specification says "All presure vessel shall be designd and fabricated to ASME Sec VIII Div 1 as per desin data (Design data given)
Question 1:: Noting that ASME Sec VIII Div 1 UCS does not call for simulation heat treatment for P1 material, yet as per the clause 7.4 of SA 420 WPL 6 (As embedded below)Is it necessary (In order to meet the ASME requirement) for the vessel manufacturer to inform the fitting supplier that the vessel is going to be used in a vessel and that the vessel is going to be post weld heat treated and the fitting need simulation heat treatment?
Clause 7.4 from A 420 WPL6
7.4 When the fittings are to be post-weld heat treated after being welded by the purchaser and when so specified in the order, the test specimens shall be subjected to the same post-weld heat treatment. The purchaser shall use the postweld heat treatment shown in Table 2, unless otherwise
specified in the order.
Question 2) Does the words " When specified so" imply an obligation on the part of vessel manufacturer to inform the manufacturer of the fitting?
Question 3) IF the vessel manufactuer does mention the vessel is being heat treated, is it mandatory for the fitting manufacturer to subject the test specimens to the same post-weld heat treatment prior to testing (Even if the vessel manufacturer does not call for Simulated testing).