rls911
Mechanical
- Mar 30, 2005
- 1
Dear Members,
I am looking for your thoughts and comments on the following:
We are in the process of constructing a new boiler with steam outlet design conditions of 1750 psig @ 950 - 1000 deg. F. The boiler manufacturer will be supplying the outlet header (boiler external piping) as SA335-P22. Our normal standards for this application would be to continue on with P/F22 for the pipe, fittings, and valves.
But we have been presented a more economical alternative of SA335-P91 (lighter wall thickness + smaller header diameter = less cost). The design would include F91 fittings but would use F22/WC9 for large bore valves and F11 for small bore valves (socket welded valves).
Other than a potential capital cost savings, are there any other benefits to using the P91?
After reading some of the previous posts on P91, I am not so sure we are goiing down the right path. ie.
- disimilar weld joints.
- transition pieces at the valves.
- PWHT everywhere.
- Critical QA/QC of welding process.
- potential code changes on the material specifications.
- lack of clarity/consensus between the piping codes and metallurgists on handling the PWHT.
I am looking for your thoughts and comments on the following:
We are in the process of constructing a new boiler with steam outlet design conditions of 1750 psig @ 950 - 1000 deg. F. The boiler manufacturer will be supplying the outlet header (boiler external piping) as SA335-P22. Our normal standards for this application would be to continue on with P/F22 for the pipe, fittings, and valves.
But we have been presented a more economical alternative of SA335-P91 (lighter wall thickness + smaller header diameter = less cost). The design would include F91 fittings but would use F22/WC9 for large bore valves and F11 for small bore valves (socket welded valves).
Other than a potential capital cost savings, are there any other benefits to using the P91?
After reading some of the previous posts on P91, I am not so sure we are goiing down the right path. ie.
- disimilar weld joints.
- transition pieces at the valves.
- PWHT everywhere.
- Critical QA/QC of welding process.
- potential code changes on the material specifications.
- lack of clarity/consensus between the piping codes and metallurgists on handling the PWHT.