Hi All,
I am working as a Standards Manager in a water utility Company and currently we are having issues on the applicability of the backfill material we are using on our trenches and the right compaction method to be applied. I have attached a drawing of a typical trench section. As you can see, for the bedding and pipezone area, we are using Sand Class S1 (0-6mm size). For the backfill above the pipezone, it's either we use native materials (if suitable)/ imported backfill/ Sand Class S1 (0-6mm in size). The following are my concerns:
1. For the bedding and pipezone area.
2. For the backfill above the pipezone.
The trenches I am referring to are situated on highway pavements subject to truck loadings (HS20 loading). Sorry for my long querry at least I think I provided the needed details for you more experienced professionals to provide your opinions/ answers to my questions. I am looking forward to your responses.
I am working as a Standards Manager in a water utility Company and currently we are having issues on the applicability of the backfill material we are using on our trenches and the right compaction method to be applied. I have attached a drawing of a typical trench section. As you can see, for the bedding and pipezone area, we are using Sand Class S1 (0-6mm size). For the backfill above the pipezone, it's either we use native materials (if suitable)/ imported backfill/ Sand Class S1 (0-6mm in size). The following are my concerns:
1. For the bedding and pipezone area.
a.) Is the Sand that I specify really suitable?
b.) The only compaction method we are applying in this area is by "flooding", is this suitable?
c.) If flooding is ok, how can we know that the resulting compaction is sufficient? Our specifications states that Field Density test is not required in the pipezone area. Is this because of the difficulty compacting this portion of the trench? Any thoughts?
d.) Can anyone suggest any other efficient compaction method in this area?
2. For the backfill above the pipezone.
a.) If the native material/ imported backfill (other than Sand (0-6mm in size)) will be used, conventional procedures are
implemented that is, taking the sample for laboratory testing (proctor test) to determine optimum moisture content and
maximum dry density. The material will then be compacted on site (mechanical means) every 150mm lifts then an FDT will be
performed to know if the Contractors achieved 95% compaction. Did I miss something? Can we allow larger lifts like 200mm,
250mm, 300mm, etc.? What might be the implication of allowing larger lifts?
implemented that is, taking the sample for laboratory testing (proctor test) to determine optimum moisture content and
maximum dry density. The material will then be compacted on site (mechanical means) every 150mm lifts then an FDT will be
performed to know if the Contractors achieved 95% compaction. Did I miss something? Can we allow larger lifts like 200mm,
250mm, 300mm, etc.? What might be the implication of allowing larger lifts?
b.) If the backfill material is Sand Class S1 (0-6mm in size):
b.1. Is this material really suitable?
b.2. Is the conventional procedure I mentioned in 2.a above is still applicable?
b.3. Our specification allows compaction of Sand(0-6mm in size) by "flooding".Is this really suitable or efficient? How can
we know that the resulting compaction is sufficient enough? Can the actual compacted density by flooding be compared
with the maximum dry density taken from the proctor test? Does compaction by flooding be able to achieve 95% compaction?
How long after the application of water by flooding can you perform a Field Density Test?
b.2. Is the conventional procedure I mentioned in 2.a above is still applicable?
b.3. Our specification allows compaction of Sand(0-6mm in size) by "flooding".Is this really suitable or efficient? How can
we know that the resulting compaction is sufficient enough? Can the actual compacted density by flooding be compared
with the maximum dry density taken from the proctor test? Does compaction by flooding be able to achieve 95% compaction?
How long after the application of water by flooding can you perform a Field Density Test?
The trenches I am referring to are situated on highway pavements subject to truck loadings (HS20 loading). Sorry for my long querry at least I think I provided the needed details for you more experienced professionals to provide your opinions/ answers to my questions. I am looking forward to your responses.