CanuckPE
Structural
- Apr 14, 2021
- 21
I've specified a thin layer (2") of sand directly under concrete for several slab-on-grade projects per a professional development course I participated in a few years ago. As I understand it, wetting the sand prior to concrete placement helps mitigate warping of thinner slabs during curing by equalizing moisture migration from the top and bottom of the slab. I've done about five projects with the sand layer, and the field reviews went reasonably well without any negative feedback from the client or contractors. For all five projects, the slabs were relatively thin (as thick as 8" with a single layer of reinforcing steel).
I just field reviewed a mat foundation with a relatively heavy reinforcing steel cage on it, and I utilized the thin layer of sand approach. There is a 20M bar @ 12" o/c e/w top and bottom. The mat thickness is between 22" and 12" depending on the location. The bar tying folks built the cage in-situ and set the cage on brick chairs about every four feet on centre. I'm told the compaction tests were completed for several inches of structural fill below the sand.
Upon field review of the cage, I found the brick chairs were embedded into the sand and the bottom cover is now way under that specified (3"). I haven't done any checks on bearing pressure (cage weight over bearing area of the bricks), but I suspect the weight of the cage divided by the bearing area of the bricks results in a high pressure. The sand is not not very compact, as it's been disturbed by all of the construction activity, but it's under a double layer of reinforcing steel, so I think further mechanical compaction is out of the question unless the cages are removed. Perhaps we could hand-tool it. If I had been the contractor, I would have had the cages preassembled, chairs prepped/measured then set the cages onto the chairs using a telehandler, but I did not specify this technique.
A couple of questions:
1) What are your thoughts on the relatively loose layer of sand between better-compacted fill layer below and the reinforced concrete above? Would it contribute significantly to settlement/differential settlement if left loose as it is? Should we remove the layer of sand? Should we try to hand-tool for compaction?
2) Does anyone have any similar experiences with reinforcing steel resting on a sand layer for S-O-G? What are your experiences?
I just field reviewed a mat foundation with a relatively heavy reinforcing steel cage on it, and I utilized the thin layer of sand approach. There is a 20M bar @ 12" o/c e/w top and bottom. The mat thickness is between 22" and 12" depending on the location. The bar tying folks built the cage in-situ and set the cage on brick chairs about every four feet on centre. I'm told the compaction tests were completed for several inches of structural fill below the sand.
Upon field review of the cage, I found the brick chairs were embedded into the sand and the bottom cover is now way under that specified (3"). I haven't done any checks on bearing pressure (cage weight over bearing area of the bricks), but I suspect the weight of the cage divided by the bearing area of the bricks results in a high pressure. The sand is not not very compact, as it's been disturbed by all of the construction activity, but it's under a double layer of reinforcing steel, so I think further mechanical compaction is out of the question unless the cages are removed. Perhaps we could hand-tool it. If I had been the contractor, I would have had the cages preassembled, chairs prepped/measured then set the cages onto the chairs using a telehandler, but I did not specify this technique.
A couple of questions:
1) What are your thoughts on the relatively loose layer of sand between better-compacted fill layer below and the reinforced concrete above? Would it contribute significantly to settlement/differential settlement if left loose as it is? Should we remove the layer of sand? Should we try to hand-tool for compaction?
2) Does anyone have any similar experiences with reinforcing steel resting on a sand layer for S-O-G? What are your experiences?