cher122976
Civil/Environmental
- Mar 16, 2009
- 49
There is an existing sanitary pump station on site that has gravity feed from two smaller building and a 3" force main from it. We have a proposed sanitary system collecting sewage from 10 smaller facilities. We want to gravity drain to the existing pump station. What type of issues need to be looked at to tell if this is feasible?
We also might need to put a new pump station in on our site and connect to that existing 3" line. IS that normally feasible?
My expertise is in another area so any help would be welcome
Thanks
We also might need to put a new pump station in on our site and connect to that existing 3" line. IS that normally feasible?
My expertise is in another area so any help would be welcome
Thanks