johnyt79
Civil/Environmental
- Mar 4, 2010
- 4
I've encountered a design challenge where we are required to cross under a low flow creek with a 200mm sanitary sewer main. The usual method is to cross the creek with a segment of ductile iron pipe, encase it in concrete, and then place 200mm di. cobbles on top.
However, the enviromental team wont allow us to pour, or use concrete around the creek area.
One path is to embed rip-rap, somewhat building an underground rock-stack and placing the pipe behind to support to prevent it from moving...
Anyone out there with experience or thoughts?
thanks!
However, the enviromental team wont allow us to pour, or use concrete around the creek area.
One path is to embed rip-rap, somewhat building an underground rock-stack and placing the pipe behind to support to prevent it from moving...
Anyone out there with experience or thoughts?
thanks!