Could someone please clarify what is the correct way to detail the connection between the scissor truss and stud wall top plate. I have read several threads on this website regarding this, but it doesn't seem like there has been any clarification.
Is it incorrect to provide connection at both ends of the scissor truss to prevent lateral thrust assuming that the wall would move with the truss. My thought is to install the connections after the dead load has been placed.
The project I have this on is a 40' x 80' church located in the middle tennesse area. 2/3 of the roof is scissor trusses and the other 1/3 is common roof trusses.
My huge dilemma is over the top plate connection and top plate design.
If anyone has encountered this problem, please help shed some light.
Thank you,
Val
Is it incorrect to provide connection at both ends of the scissor truss to prevent lateral thrust assuming that the wall would move with the truss. My thought is to install the connections after the dead load has been placed.
The project I have this on is a 40' x 80' church located in the middle tennesse area. 2/3 of the roof is scissor trusses and the other 1/3 is common roof trusses.
My huge dilemma is over the top plate connection and top plate design.
If anyone has encountered this problem, please help shed some light.
Thank you,
Val