Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations GregLocock on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Scoring

Status
Not open for further replies.

Crocodile22

Computer
Apr 23, 2013
3
I uploaded a picture of poured concrete steps. I didn't realize the contractor didn't put a score mark at the bottom of the steps in case of cracking. My question is "should there be a score mark at the bottom of the steps?" 4000 PSI concrete

I have a picture of the forms also.

 
Replies continue below

Recommended for you

There should have been an isolation joint there; however, it is not critical. You will get a crack there, but it will likely occur at the horiz/vert transition. Scoring would have made it a bit neater, but you would get the same result.
 
You can do that, but likely the crack has already occurred....look very, very closely!
 
Status
Not open for further replies.