dskurnik
Electrical
- May 19, 2007
- 3
I am placing a 9 ft wide, 22.5 ft long bottomless arch box culvert in a creek. There is no firm data for 100 year peak volume. The dimensions are set by fish passage requirements, rather than hydraulic. The capacity is more than 3X compared to upstream culverts on the same creek.
The design calls for concrete footings placed below the streamgrade. Since this is a small project, the cost of concrete is cheaper than detailed geotechnical analysis. Is there a rule of thumb to estimate the necessary depth for the bottom of the footings to ensure that it is below the scour depth?
The design calls for concrete footings placed below the streamgrade. Since this is a small project, the cost of concrete is cheaper than detailed geotechnical analysis. Is there a rule of thumb to estimate the necessary depth for the bottom of the footings to ensure that it is below the scour depth?