HgTX
Civil/Environmental
- Aug 3, 2004
- 3,722
Need a sanity check.
QW-251.2 appears to say that the supplementals (e.g., additional restrictions on minimum thickness & maximum heat input) kick in automatically whenever Charpies are required.
We have WPS/PQR provided by a sub. They have Charpies, but don't seem to have worried about the thickness & HI limitations--and the customer's engineer doesn't seem to have worried about this either, even though they critiqued other aspects of the WPS. Sub says they've had no end of customers' engineers reviewing their procedures, closely enough to require spelling correction on electrode trade names, and no one has ever made them cut their thickness range to start at the tested thickness, and cut the electrical parameters down to what was on the PQR (which would be a big cut, and not a good one for performance, if they ran their PQR in the comfortable middle).
So I sanity-checked with a buddy at yet another company and he said more or less the same, that he's never required from a sub nor been required by a customer to work to the supplementals unless said supplementals have been written into the contract.
So, am I overreading 251.2? Or is that an instruction to the EOR for when they should be specifying the supplementals and it's not an automatic requirement? Or is there an automatic requirement that just gets underenforced by the WPS-reviewing engineer community? I don't want to force the sub to run additional tests (or worse, force them into an abnormally low part of their operating range) if this isn't normal practice.
Hg
QW-251.2 appears to say that the supplementals (e.g., additional restrictions on minimum thickness & maximum heat input) kick in automatically whenever Charpies are required.
We have WPS/PQR provided by a sub. They have Charpies, but don't seem to have worried about the thickness & HI limitations--and the customer's engineer doesn't seem to have worried about this either, even though they critiqued other aspects of the WPS. Sub says they've had no end of customers' engineers reviewing their procedures, closely enough to require spelling correction on electrode trade names, and no one has ever made them cut their thickness range to start at the tested thickness, and cut the electrical parameters down to what was on the PQR (which would be a big cut, and not a good one for performance, if they ran their PQR in the comfortable middle).
So I sanity-checked with a buddy at yet another company and he said more or less the same, that he's never required from a sub nor been required by a customer to work to the supplementals unless said supplementals have been written into the contract.
So, am I overreading 251.2? Or is that an instruction to the EOR for when they should be specifying the supplementals and it's not an automatic requirement? Or is there an automatic requirement that just gets underenforced by the WPS-reviewing engineer community? I don't want to force the sub to run additional tests (or worse, force them into an abnormally low part of their operating range) if this isn't normal practice.
Hg