"When any part of the cladding thickness is specified as an allowance for corrosion, such added thickness shall be removed before mill tension tests are made."
In our case, we are cladding a CS plate with a SS plate using a solid state welding process. Does the above statement in the spec. mean that the corrosion allowance needs to be removed for tension tests that are to be performed at the mill for the SS plate only or after the cladding process for the CS plate cladded with the SS plate?
In our case, we are cladding a CS plate with a SS plate using a solid state welding process. Does the above statement in the spec. mean that the corrosion allowance needs to be removed for tension tests that are to be performed at the mill for the SS plate only or after the cladding process for the CS plate cladded with the SS plate?