newweldeng09
Mechanical
- Oct 31, 2008
- 84
Situation: I have a P1 case that has P1 nozzles welded to it that has been post weld heat treated in a furnace charge. It was finished machined and has been sent to hydro. test. During testing, a leak was discovered due to a mis-machined area on an internal feature of the case, which is not connected to the nozzle to case welds. A base metal weld repair needs to be performed. Less than 1/16" of weld metal is going to remain after final machining to repair this area. Per UCS-56(a), (2nd Par.), all welds in pressure vessels shall be given a PWHT at a min. temperature in Tables UCS-56 and UCS-56.1 when the nominal thickness exceeds the limits in those tables. In this case, nominal thickness, as defined in UW-40(f) is the depth of the repair, which is well under the 1.5" of Note 2(a) and the 1.25" of Note 2(b) in Table UCS-56. Therefore, PWHT does not need to be performed. However, in UCS-56(e), vessels that have been PWHT in accordance with the requirements of this paragraph shall again be PWHT after welded repairs have been made.
Is PWHT to be performed following this repair because the case has been PWHT previously or does UCS-56(e) apply only to weld repair areas on the nozzle and case close to the weld and on the weld itself?
Is PWHT to be performed following this repair because the case has been PWHT previously or does UCS-56(e) apply only to weld repair areas on the nozzle and case close to the weld and on the weld itself?