Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations SSS148 on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Seismic Tie Beams on Long Span Frames

Status
Not open for further replies.

TLHS

Structural
Jan 14, 2011
1,600
I have a fun situation. We are looking at the foundation design for a very large moment frame supported fabric shelter (no sidewalls) on a site adjacent to the water with poor ground conditions. The geotech folks are going to mitigate some of the liquifaction issues, but it's still not a pristine site. By my read of the National Building Code of Canada, the footings for this structure need to be tied together to avoid differential foundation movement.

There is an axial force requirement in the code. My issue comes from the span in question. The superstructure has a portal frame span of 20+ meters. That means that in one direction my tie beams will run that long. A slab on grade is not preferred from an economical standpoint, if it can be avoided, so there's no floor diaphragm. For any practical size of tie beam, this is a slender compression member. Realistically, though, how would I examine this? If the soils are competent, I could probably calculate out enough bracing capacity to keep it from buckling from selfweight friction and a bit of soil pressure. Counting on the soil to be competent, though, feels like it goes against the purpose of the tie beams. ACI and CSA A23.3 seems to have a maximum required size (450mm). If I use that, do I just get to assume there isn't a buckling issue? If I even wanted to consider buckling, it doesn't seem like there'd be a rational basis to use since this isn't a purely analytical design basis. How do you do a P-Delta analysis when there's an undefined lateral displacement that could be happening at the same time? I could attempt to brace the footings against skew to limit p-delta similar to how a floor diaphragm would, but I run into the same issue of having no real load basis for the design of that bracing, since it isn't really just bracing against buckling, it would be bracing against some sort of undefined differential ground movement.
 
Replies continue below

Recommended for you


The followings are from ACI 318-14 and ASCE 7-16

- ACI 318 ; 18.13.3.2 ...grade beams designed to act as horizontal ties between pile caps or footings shall be sized such that the smallest cross-sectional dimension shall be at least equal to the clear spacing between connected columns divided by 20, but need not exceed 18 in.

ASCE 7-16 12.13.6.2 ;

- Individual pile caps, drilled piers, or caissons shall be interconnected by ties. All ties shall have a
design strength in tension or compression at least equal to a force equal to 10% of SDS times the larger pile cap or column.. ( For SDC C,D,E,F..

- 12.13.8.2 Foundation Ties. Individual pile caps, drilled piers, or caissons shall be interconnected by ties. In addition, individual spread footings founded on soil defined in Chapter 20 as Site Class E or F shall be interconnected by ties...


You may still consider the use of reinforced concrete SOG ..

If you decide to use tie beams , you should provide competent surrounding soil ( compacted granular ) backfill which will provide restraint against buckling.

You may provide more info ( SDC , soil conditions, a sketch of the frame...) to get better responds..
 
I would consider it to be like a "horizontal pile"....a compression member where buckling is resisting by the confinement of the surrounding soil. Even not-so-great soil is capable of providing adequate buckling resistance to piles.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor