AusLee
Electrical
- Sep 22, 2004
- 259
Hello,
Please i have a threefold question:
1. I have a generator room near an auditorium, someone proposed the use of "low RPM" gensets as a first measure towards noise reduction. Is it true that low RPM gensets are less noisy than normal 1500/1600RPM generators? I have a financial study that shows their fincancial efficacy overt the service hours, but nothing electrical?
2. The maintenance company wants to change the oil every 250 hours. My question is: is an hour of service counted as 60 minutes of runtime, or are there other conditions such as: 10 minutes at Full Load count more than half an hour at 30% of the load? The genset is 1,000kVA.
3. The installation was served by a 1,000kVA generator. The client took that out and put 2x500kVA generators (in case of low load, only one will go in service). Now he changed his idea: he wants to separate the main distribution board in 2, and each 500kVA genset supplies one half. So i will take out the 1,600A breaker in the MDB and replace it with two 800A breakers, one for each side, plus a third one as a "tie-bus" breaker to link the two parts in case of supply from the 1x1,000kVA transformer. My question is: is there any weird neutral arrangemets i should watch out againt? the system is supposedly a TN-S.
Thanks!
Please i have a threefold question:
1. I have a generator room near an auditorium, someone proposed the use of "low RPM" gensets as a first measure towards noise reduction. Is it true that low RPM gensets are less noisy than normal 1500/1600RPM generators? I have a financial study that shows their fincancial efficacy overt the service hours, but nothing electrical?
2. The maintenance company wants to change the oil every 250 hours. My question is: is an hour of service counted as 60 minutes of runtime, or are there other conditions such as: 10 minutes at Full Load count more than half an hour at 30% of the load? The genset is 1,000kVA.
3. The installation was served by a 1,000kVA generator. The client took that out and put 2x500kVA generators (in case of low load, only one will go in service). Now he changed his idea: he wants to separate the main distribution board in 2, and each 500kVA genset supplies one half. So i will take out the 1,600A breaker in the MDB and replace it with two 800A breakers, one for each side, plus a third one as a "tie-bus" breaker to link the two parts in case of supply from the 1x1,000kVA transformer. My question is: is there any weird neutral arrangemets i should watch out againt? the system is supposedly a TN-S.
Thanks!