Simba13
Structural
- May 19, 2020
- 105
Afternoon all,
I have a quick question regarding ACI's anchorage to concrete provisions. My boss has me designing a holdown for a cantilever, it is supposed to be an all-thread bolt drilled and epoxied into concrete. So I go to CH 17 of ACI 318 to get an idea of my capacity and it says that there has to be a load test to verify the strength of the connection, makes sense. Here is my question, Simpson's SET-3G Epoxy says it was tested under the provisions of ACI 355.4, so does there need to be a load test on the connection as a whole or is it sufficient that the epoxy satisfies the provisions?
Thanks,
I have a quick question regarding ACI's anchorage to concrete provisions. My boss has me designing a holdown for a cantilever, it is supposed to be an all-thread bolt drilled and epoxied into concrete. So I go to CH 17 of ACI 318 to get an idea of my capacity and it says that there has to be a load test to verify the strength of the connection, makes sense. Here is my question, Simpson's SET-3G Epoxy says it was tested under the provisions of ACI 355.4, so does there need to be a load test on the connection as a whole or is it sufficient that the epoxy satisfies the provisions?
Thanks,