eimckay
Civil/Environmental
- Sep 8, 2006
- 1
I am trying to simulate a closed valve to a treatment plant in sewerCAD to determine how long it will take until there is surcharge from the shallowest manhole in the model. I have run an EPS (Extended Period Simulation) but it did not work as I had intended it to. When I ran the cartoon of it in sewerCAD the sewage did not back up. I tried to create a closed valve situation by making the outfall junction (treatment plant) a user-defined tailwater elevation much above my HGL so the water would have no where to go therefore backing up into the pipe. The other area I am not sure about is the area of annotation. I assumed i wanted to annotate full pipe capacity but that did not work either. Does anyone have any suggestions?