cap4000
Civil/Environmental
- Sep 21, 2003
- 555
I have a situation with a 50 foot high nearly vertical well cemented shale cliff with a residential development 20 feet away from its base. Does anyone have a safe rock bank cut typical formula. For example clay cohesive soils are temporarily stable depending on its cohesion and friction values. Rock is a whole different animal and depends mainly on the tension crack formations and locations. Any feedback would be appreciated as I am currently designing an anchored rock fall netting for this situation.