ampersand
Structural
- Sep 2, 2005
- 30
So here's a (hopefully) simple question...
Contractors always want to pour concrete retaining walls in two pours, with a construction joint at the bottom of the wall/top of the footing. If we call for a "construction joint" on our details, are we jutified in assuming that the full shear strength (2*sqrt(f'c)*b*d) can be developed at the joint.
I've heard that this is standard practice, but I can't help but doubt the integrity of these joints.
Thanks in advance...
Contractors always want to pour concrete retaining walls in two pours, with a construction joint at the bottom of the wall/top of the footing. If we call for a "construction joint" on our details, are we jutified in assuming that the full shear strength (2*sqrt(f'c)*b*d) can be developed at the joint.
I've heard that this is standard practice, but I can't help but doubt the integrity of these joints.
Thanks in advance...